Housing construction slowdown continues into 2025

Share this edition:

Across the nation, there has been a slowdown in housing construction. Between 2020 and 2025, the number of months it takes to build a house increased by 34 per cent across Australia, while building material costs increased by 35 per cent – partly due to increased demand.

The time it takes to build a house, on average across Australia, increased from about eight months and a half to about a year. Between 2020 and 2025, the average time required to build a house has increased by:

  • 71 per cent in Western Australia (with material costs 37 per cent more expensive);
  • 34 per cent in South Australia (with material costs 35 per cent more expensive);
  • 34 per cent in Queensland (with material costs 37 per cent more expensive);
  • 31 per cent in New South Wales (with material costs 32 per cent more expensive);
  • 16 per cent in Victoria (with material costs 36 per cent more expensive); and
  • 15 per cent in Tasmania (with material costs 37 per cent more expensive).

Kevin You

Dr Kevin You is a Senior Fellow at the Institute of Public Affairs
Stay up to date

Sign up to our newsletter to stay up to date with the IPA’s work

Support the IPA

If you liked what you read, consider supporting the IPA. We are entirely funded by individual supporters like you.

Related Posts

Education ‘industry’ not the bonanza we’re sold

When I was a teenager starting to take an interest in economics,...

Adam Creighton on Sharri News24 – 10 September 2026

Steve Price: Okay. Joining me now, IPA Chief Economist Adam Creighton and...

Daniel Wild on Credlin News24 – 10 September 2026

Peta Credlin: Thank you. Let’s go now to my Panel, National Affairs...

Labor’s digital duty of care privatises political censorship

Political elites have much to fear from the ‘little-people’ talking among themselves....